147

Using BESTCOMS, set the SCL high limit to 50% greater than the metered current. .......... ________

Using BESTCOMS set the SCL high limit time delay at 5 seconds. ..................................... ________

Enable stator current limiting. ................................................................................................ ________

Perform a step response into the SCL limit. .......................................................................... ________

Verify stable performance and speed of response. .............................................................. ________

Repeat with unit supplying 30% load at 0.8 leading PF in Droop mode. .............................. ________

If the response time is too slow, increase the SCL gain (Ki and Kg) and repeat the test.

Verify stable performance of the SCL by testing the machine from 25% through 100%
real-power loading, underexcited. ......................................................................................... ________

Increase the excitation above the UEL limit. ......................................................................... ________

Enter the final, operating UEL values. ................................................................................... ________

Var Test (If Applicable)

Verify that Var mode is nulled to AVR. .................................................................................. ________

Verify that all null status indicators indicate a null condition. ................................................ ________

Verify that the Var pre-position mode is disabled or the external pre-position contacts
are open. ................................................................................................................................ ________

In the following step, be prepared to transfer back to AVR mode if the excitation voltage increases
suddenly.

Transfer to Var. ...................................................................................................................... ________

Set kW for 25% output. .......................................................................................................... ________

Adjust vars to 30% of rated. .................................................................................................. ________

Monitor the field voltage to determine performance of the following step.

Using BESTCOMS, perform a 5% step response stability test. ............................................ ________

If necessary, increase the var gain (Ki and Kg) to quicken the response and repeat the
test. ........................................................................................................................................ ________

Power Factor Test (If Applicable)

Verify that PF mode is nulled to Var mode. ........................................................................... ________

Verify that all null status indicators indicate a null condition. ................................................ ________

Verify that the PF pre-position mode is disabled or the external pre-position contacts
are open. ................................................................................................................................ ________

In the following step, be prepared to transfer back to PF mode if the excitation voltage increases
suddenly.

Transfer to PF. ....................................................................................................................... ________

Adjust the power factor for 0.9 lagging. ................................................................................. ________

Perform a step response by changing the PF setpoint to 0.85 lagging to determine
stability. .................................................................................................................................. ________

If necessary, increase the PF gain (Ki and Kg) to quicken the response and repeat the
test. ........................................................................................................................................ ________

Recommended PSS Testing

The following paragraphs describe desired tests to evaluate and confirm stabilizer operation in your
system. For specific testing and commissioning procedures, contact Basler Electric Technical Sales
Support at +1 618-654-2341.