Festo Электромотор MTR-DCI User Manual
Page 103

5. Commissioning
5-25
Festo P.BE-MTR-DCI-IO-EN en 1209d
If there is a 1-signal at the ENABLE input, the controller and
the power end stage will be switched on. The current position
set will be processed at the next START signal.
Pin
Status
ENABLE
I6
1-signal
Controller and power end stage are
switched on
0-signal
Controller and power end stage are
switched off
1
> 0
Quit faults
READY O1
Ready to operate. All prerequisites for starting a positioning
procedure are fulfilled.
Pin
Level
READY
O1
0
System is not ready to operate.
– ENABLE is not set
or
– there is a fault
1
System is ready to operate.
– ENABLE is set
and
– no fault
MC O2
Motion complete
Shows that a positioning order has been completed and that
the START input has been reset.
Pin
Status
MOTION COMPLETE
O2
0-signal
Positioning procedure is being carried out or
there is still a START signal at 1.
1-signal
Positioning task is completed