Power and ground considerations – Meridian America Link/Customer Controlled Routing User Manual

Page 124

Advertising
background image

106 Chapter 6: Site survey/installation checklist

553-3202-210 Standard October 1998

Power and ground considerations

Your moduleÕs power source is either 110 V AC or 208 V DC. In each case,
refer to the following NTPs to ensure that proper power and grounding
requirements are met.

¥

Application Equipment Module Installation Guide (NTP 553-3201-200)

¥

MPP600 Modular Power Plant: Description, installation, operation,
and maintenance manual
(NTP 167-9021-105)

¥

Meridian 1 Applications System 600/48 Description, Installation,
Operation and Maintenance Manual
(NTP 167-9021-111)

Use the following checklist to check the condition of the power source at
your site.

Table 23
Power and ground considerations for AC-powered modules

Power and ground considerations

Yes

No

Is there a separately grounded 110 V AC
outlet for power equipment?

Is an approved ground system in place?

Has the approved power and ground been
measured?

Does the approved power and ground system
meet the requirements outlined in Power
Engineering
(NTP 553-3001-151)?

Advertising