TOHO ELECTRONICS TTM200 User Manual

Page 223

Advertising
background image

48-7009-E

6-75

Time Setting

SEt21

PGF

Setting Contents

Initial

Value

4

H/MP

Time Setting 3

0

0

Step Time (Hr./Min.)

1

Soak Time 1(Hr./Min.)

2

Soak Time 2 (Hr./Min.)

3

Step Time (Min./Sec.)

4

Soak Time 1 (Min./Sec.)

5

Soak Time 2 (Min./Sec.)

Step Time:After a lapse of set time, it will proceed to the
next step.

Soak Time 1:Once it enters within the set WAIt range,

the time count starts. After a lapse of time,
it will proceed to the next step.

Soak Time 2:Only when it enters the set WAIt range,

the time count starts. After a lapse of
time, it will proceed to the next step.

4 Time Unit Setting (H/MP)

It sets the time unit and countdown condition.

With the Step Time* Setting (tIM*), the step duration time for every Step can be set, and the condition of

the countdown against this value can be set.

After the set time elapse (completion of countdown), it will proceed to the next step.

Setting Range

0, 3: (Step Time) The countdown starts regardless of the condition of PV/SV value.

1, 4: (Soak Time 1) The countdown starts once the PV value is entered within the set wait range.

2, 5: (Soak Time 2) Countdown is done if the PV value is entered only to the set wait range (①+②+③). The countdown

does not take place when the PV value is outside the wait range.

SV3

PV

STEP TIME

SOAK TIME1

SOAK TIME2

WAIT RANGE

SV

NOTE: The determination is made with the set SV value even if the ramp is being set.
NOTE: When Soak Time 1 and Soak Time 2 is selected, the countdown starts by the comparison between the PV and SV
value. It will be determined by PV Value, SV*(*=1 to 8) and wait range (WAIt).
NOTE: The countdown starts with the comparison of the PV Value and SV Value, but when the ramp function is being
used, the countdown starts when it becomes; Present SV Value = SV*(*=1 to 8).
NOTE: When the step time is being set, the ramp function cannot be used.
NOTE: SV3 is a Control Setting Value.