Procedure 14 earthing the cabinets or chassis (uk), Multiple, Multiple pieces of equipment in an – Nortel Networks 1000M User Manual

Page 134: Multiple pieces of

Advertising
background image

134

Installing the system ground

Procedure 13

Earthing the cabinets or chassis (UK)

Step

Action

1

Connect a protective and functional earth wire from the earthing strip
on the Krone Test Jack Frame to the earth at the building entry point.

Use a green/yellow wire no thinner than 10 mm

2

(3/8 in.).

2

In each cabinet or chassis, connect an earth wire from the ground
lug in the cabinet (see

Figure 55 "Ground/Earth lug in the NTAK11

system cabinets" (page 131)

) or chassis (see

Figure 56 "Grounding

a chassis and chassis expander pair" (page 132)

) to the earth

connection at the Test Jack Frame.

Use a green/yellow wire no thinner than 10 mm

2

(3/8 in.). For the

Cabinet system, route the earth wire through the third groove from
the left in the bottom portion of the cabinet.

Place a DO NOT DISCONNECT tag on the earthing wire.

3

Measure the resistance of the earth between the Krone Test Jack
Frame and the Main Cabinet or Chassis frame earth.

The resistance must not be more than 0.25 ohms at 30 amperes.

—End—

Multiple pieces of equipment in an equipment rack/cabinet

For a Chassis system with multiple pieces of equipment installed in an
equipment rack/cabinet, make a separate ground connection from each
piece of equipment to the NTBK80 grounding block. Consider each chassis
and chassis expander pair, however, as one ground. Jumper the chassis
expander ground to the chassis ground. See

Figure 58 "Grounding multiple

pieces of equipment in a rack" (page 135)

.

If a piece of Data Communication Equipment installed in a rack/cabinet
does not have a grounding lug, ground the rack to the NTBK80 grounding
block. See

Figure 58 "Grounding multiple pieces of equipment in a rack"

(page 135)

.

When you ground the rack to the grounding block, the equipment is
grounded using the Single Point Grounding method, as shown in the
grounding requirements in the chapters on system and site requirements
in Communication Server 1000M and Meridian 1 Small System Planning
and Engineering (NN43011-220)
.

Nortel Communication Server 1000

Communication Server 1000M and Meridian 1 Small System Installation and Commissioning

NN43011-310

01.04

Standard

Release 5.0

13 May 2008

Copyright © 2008, Nortel Networks

.

Advertising