NTAK76 battery unit installation

151

Figure 67
Cable connections

NTAK76 battery unit installation

Follow

Procedure 17 "Installing the NTAK76 battery unit" (page 151)

to

install an NTAK76 battery unit. Repeat the procedure for each system
cabinet being installed.

Note: The system external ground must be installed before installing
the battery backup unit.

Procedure 17

Installing the NTAK76 battery unit

Step

Action

1

Unpack the NTAK76 battery unit and place it according to the
equipment layout plan.

The battery unit must be installed within 0.9 m (3 ft) of the
cabinet it is serving.

The battery unit must be installed beside or below the cabinet,
not above.

If installed below, the minimum clearance from the top of the
NTAK76 to the bottom of the wall-mounted cabinet is 0.6 m (2 ft).

The battery unit should be installed in an open, well-ventilated
area.

Nortel Communication Server 1000

Communication Server 1000M and Meridian 1 Small System Installation and Commissioning

NN43011-310

01.04

Standard

Release 5.0

13 May 2008

Copyright © 2008, Nortel Networks

.

Advertising