Steps for commissioning – Festo Кабели и принадлежности User Manual

Page 150

Advertising
background image

4. Commissioning

4−6

Festo P.BE−SPC200−EN en 0901d

Steps for commissioning

In order to commission axes, you must first create and save
the desired hardware configuration. The individual axes and
then the complete system can be commissioned.

The following steps are necessary for commissioning with the
control panel:

1. Create the desired hardware configuration

2. Save the hardware configuration (actual configuration) as

the nominal configuration (see section 4.4.1)

3. Commission the connected axes (see section 4.4.2)

4. Commissioning the system

When the hardware configuration has been saved, the indiĆ
vidual axes can be configured and commissioned.

Commissioning pneumatic axes

The following list provides an overview of the activities which
are necessary for commissioning pneumatic axes when the
hardware configuration has been saved.

1. Setting project−specific parameters

Set all axis, application and configuration data
(see section 4.4.2, step 1).

2. Check the pneumatic tubing

Carry out a movement test with the control panel or with
WinPISA (see section 4.4.2, step 2).

3. Only for DNCI:

Carry out a reference run; only possible with WinPISA
from version 4.41. Not supported by the MMI.

New feature
as from

OS 4.82

Advertising