Pumpout and refrigerant transfer procedures, Preparation, Operating the optional pumpout compressor – Carrier 17/19EX User Manual

Page 187: Pumpout and refrigerant transfer, Procedures, Pumpout and, Refrigerant transfer procedures, Pumpout, And refrigerant transfer procedures

Advertising
background image

Pumpout and Refrigerant Transfer Procedures

Preparation

The 17/19EX may come equipped with an optional pumpout compressor. The refrigerant can

be pumped for service work to either the cooler/condenser/compressor sections or the utility

vessel by using the pumpout system. The following procedures are used to describe how to

transfer refrigerant from vessel to vessel and perform machine evacuations.

Operating the Optional Pumpout Compressor

1. Be sure that the suction and the discharge service valves on the optional pumpout

compressor are open (backseated) during operation.

Figure 32

shows the location of these

valves. Rotate the valve stem fully counterclockwise to open. Front seating the valve closes

the refrigerant line and opens the gage port to compressor pressure.

2. Make sure that the compressor holddown bolts have been loosened to allow free spring

travel.

3. Open the refrigerant inlet valve on the pumpout compressor.

4. Oil should be visible in the compressor sight glass under all operating conditions and during

shutdown. If oil is low, add oil as described under Optional Pumpout System Maintenance

section. The pumpout unit control wiring schematic is detailed in

Figure 33

. The Optional

Pumpout System is detailed in

Figure 34

.