Lead/lag control – Carrier 17/19EX User Manual

Page 96

Advertising
background image

Lead/Lag Control

Lead/Lag is a control system process that automatically starts and stops a lag or second

chiller in a 2-chiller water system. Refer to

Figure 16

and

Figure 17

for menu, table, and screen

selection information. On machines that have PSIO software with Lead/Lag capability, it is

possible to utilize the PIC controls to perform the lead/lag function on 2 machines. A third

machine can be added to the lead/lag system as a standby chiller to start up in case the lead or

lag chiller in the system has shut down during an alarm condition and additional cooling is

required.
Note: Lead/lag configuration is viewed and edited under Lead/Lag in the Equipment Configura-

tion table (located in the Service menu). Lead/lag status during machine operation is

viewed in the MAINT04 table in the Control Algorithm Status table. See

Table 2

.

Lead/Lag System Requirements:

all machines must have PSIO software capable of performing the lead/lag function

water pumps MUST be energized from the PIC controls

water flows should be constant

CCN Time Schedules for all machines must be identical

Operation Features:

2 chiller lead/lag

addition of a third chiller for backup

manual rotation of lead chiller

load balancing if configured

staggered restart of the chillers after a power failure

chillers may be piped in parallel or in series chilled water flow