Checking guide vane linkage – Carrier 17/19EX User Manual

Page 199

Advertising
background image

pressure reaches test level.

Do not exceed

140 psig (965 kPa).

5. Close the charging valve on the machine. Remove the copper tube if no longer required.

Repair the Leak, Retest, and Apply Standing Vacuum Test

After pressurizing the machine, test for leaks with an electronic leak detector, soap bubble

solution, or an ultrasonic leak detector. Bring the machine back to atmospheric pressure, repair

any leaks found, and retest.

After retesting and finding no leaks, apply a standing vacuum test, and then dehydrate the

machine. Refer to the Standing Vacuum Test and Machine Dehydration in the

Before Initial

Start-Up

section.

Checking Guide Vane Linkage (Refer to

Figure 35

)

If slack develops in the drive chain, backlash can be eliminated as follows:

1. With machine shut down (guide vanes closed), remove chain guard, loosen actuator

holddown bolts and remove chain.

2. Loosen vane sprocket set screw and rotate sprocket wheel until set screw clears existing

spotting hole.

3. With set screw still loose, replace chain and move vane actuator to the left until all chain

slack is taken up.

4. Tighten actuator holddown bolts and retighten set screw in new position.

5. Realign chain guard as required to clear chain.