Final alignment, Hot alignment check – Carrier 17/19EX User Manual

Page 217

Advertising
background image

Final Alignment

The procedures and tolerance requirements for final alignment are the same as those de-

scribed in the

Near Final Alignment

section. Final alignment is performed just prior to grouting

and machine hot check. All piping, including water and steam, must be completed, but the water

and refrigerant charges need not be in place.

Hot Alignment Check

General

When all machine components have reached operating temperature (after running near full

load for from 4 to 8 hours), a hot alignment check must be made. Hot alignment check may be

made with couplings assembled or disassembled.