6.4 Cooling Fans
154
YASKAWA ELECTRIC TOEP C710656 07C YASKAWA Power Regenerative Converter - D1000 Instruction Manual
7.
Guide the lead wires through the provided hooks so the wires are held in place.
Figure 6.29
Figure 6.29 Cooling Fan Wiring: 4A0270, 4A0370
8.
Double-check the relay connector to ensure that it is properly connected.
Installing the Cooling Fan Unit
1.
Reverse the procedure described above to reinstall the cooling fan unit.
Figure 6.30
Figure 6.30 Install the Cooling Fan Unit: 4A0270, 4A0370
2.
Reattach the covers and digital operator.
3.
Turn on the power supply and set o4-03 to 0 to reset the Maintenance Monitor cooling fan operation time.
Circuit Board Cooling Fan B6
Circuit Board Cooling Fan B7
Relay Connector
Relay Connector
Hook