13.

If the PowerMonitor 5000 icon does not appear, upload and install the eds
file from the device.

14.

Check Edits Enabled, and then click OK.

15.

Click the Save icon, then OK to optimize and re-write schedule for all
connections.

The controller needs to be in Program mode for the download to happen.

16.

Put the Logix controller into Run mode and verify the new I/O
connection is running.

17.

Close out RSNetWorx software, saving the project if desired.

Data is now being written to the <ModuleName>.I.Data tag in Decimal
style. The input tag contains a mixture of different data types. The I.Data
tag must be copied into tags with the correct data type so the data can be
interpreted correctly.