Program the Redundant Controller

Chapter 7

A PIO to a primary controller may fail if a switchover occurs while the

PIO is still in process.

When the anomaly occurs and the PIO fails, you may see any of these

errors:
Failed to import file 'c\...\xxx.L5x

Object already exists

Failed to import file 'c\...\xxx.L5x

Already in request mode/state

CIP error: Problem with a semaphore

Internal Object Identifier (IOI) destination unknown

After switchover is complete, re-attempt the PIO and it completes

successfully.

There are additional considerations necessary to performing online edits:

Plan for Test Edits

Reserve Memory for Tags and Logic

Finalize Edits with Caution

Plan for Test Edits

Before you begin making edits to your redundant program while your system is

running, verify that the Retain Test Edits on Switchover setting meets your

application requirements.

If you enable the system to retain the test edits on a switchover (that is, you check

Retain Test Edits on Switchover), faults that result from the test edits can also

occur on the new primary controller after a switchover.

If you do not enable the system to retain the test edits on a switchover (that is,

you leave Retain Test Edits on Switchover unchecked), faults that result from the

test edits are not carried over to the new primary controller in the event of a

switchover.

IMPORTANT

We recommend that you leave the Retain Test Edits on Switchover setting
at the default (that is, unchcecked) to avoid faulting both controllers when
testing your edits.