11. Click Change Controller.

12. Specify the controller revision to which you are upgrading.
13. If you installed a new controller while upgrading the primary chassis

firmware, specify the new controller catalog number.

14. Click OK.
15. Access the Module Properties for each communication module in the

chassis and specify the module firmware revision to which you are

upgrading.

16. Save the project.
17. Download the project to the secondary controller.

The secondary controller is at the higher network address of the two

available for the redundant chassis.

18. After the download is complete, go offline.

TIP

If you are unable to specify the new revision, you may need to change the
Electronic Keying parameter to Compatible Keying.