Rgu installation verifications, Rgu installation verifications -11 – Rockwell Automation 2364F Regenerative DC Bus Supply Unit (RGU) User Manual
Page 81

Publication 2364F-5.01– October 2003
Installing Your RGU
7-11
RGU Installation Verifications
1. Using an ohmmeter or other continuity testing device, verify that
shorts do not exist between:
2. Verify the AC input connections.
3. If a door-mounted HIM module or SCANport connection has not
been selected, connect a HIM or GPT to the RGU’s control board
at this time.
!
ATTENTION: The verifications described in this
section must be done before turning power on to the
system. Failure to do so may result in personal injury
and/or equipment damage.
ATTENTION: Do not turn on the power if the RGU
fails any of the verifications described in this section.
Doing so may result in personal injury and/or equipment
damage.
ATTENTION: You must correct all problems before
proceeding to the next step. Failure to do so may result
in personal injury and/or equipment damage.
Source 1
Source 2
Check Below if No Short
L1
L2
❒
L1
L3
❒
L2
L3
❒
L1
PE
❒
L2
PE
❒
L3
PE
❒
R (EA1)
PE
❒
S (EA1)
PE
❒
T (EA1)
PE
❒
DC+ Bus
DC- Bus
❒
DC+ Bus
PE
❒
DC- Bus
PE
❒
DC+ Bus
TE
❒
DC- Bus
TE
❒
PE
TE
❒