This test sequentially verifies that:

Drive power wiring is correct and start-up logic is functioning

The drive and motor are correctly wired

Drive serial communications are operational

Before beginning “Initial Power-up”, please check the following:

All wiring and mounting to verify correct installation

Input voltages to ensure they do not exceed specifications for the
drive or motor.

Figure 4.1

Connection Diagram

Intro

J4

DRIVE

J1

TB1

TB1

26 +24V

20 ENABLE

21 FAULT RESET

2 RCV

3 XMT

5 COM

Phase R 1

Phase S 2

Phase T 3

Motor Gnd 4

L1 7

L2/N 8

Gnd 9/10

100-240 VAC

50/60 Hz

Single Phase

XMT

RCV

COM

Close to ENABLE drive

Close to RESET faults

Power Source

TB1

L1 7

L2/N 8

Gnd 10

L3 9

or

J2

Motor
Encoder

100-240 VAC

50/60 Hz

Three Phase

Power Source

Gnd = Pin 9 for DDM-010, DDM-020, DDM-030
Gnd = Pin 10 for DDM-075 using single phase

!