ProcessLogix Client Installation and Upgrade Procedures 5-19

9. Click Next to accept ProcessLogix Client Software as the default

Program Folder for the Client software.

10. Review the software installation details summarized in the Confirmation

window.

• If you need to make changes, click Back to access any previous

entries.

• If the details are okay, click Next to begin the Client software setup.

This may take 10 to 15 minutes to complete.

11. Skip this step if the system does not include Excel Data Exchange.

Otherwise, click Enable Macros when requested.

12. At the Setup Complete window, click the No, I will restart my computer

later option and click Finish.

13. Click Next to install the ProcessLogix Update or the ProcessLogix

Operator Workstation Update.

14. At the ProcessLogix Update or ProcessLogix Operator Workstation

Update Complete window, click Finish.

If installing Engineering Workstation, wait until after the command
windows have closed and file copying is complete. This may take a few
minutes to complete.

15. At the ProcessLogix Setup Complete window, click the No, I will restart

my computer later option and click Finish.

16. Restart the PC.

TIP

If a Microsoft Excel dialog box appears, check the Do not
show this dialog again checkbox and click OK.

ATTENTION

!

In the next step, ignore the prompt to remove any disks.
The CD must remain in the CD-ROM drive. You must
select No in Step 12.