Confirming databases are synchronized, Confirming databases are synchronized -21 – Rockwell Automation 1757-SWKIT5000 ProcessLogix R500.1 Installation and Upgrade Guide User Manual
Page 177
![background image](/manuals/579176/177/background.png)
Publication 1757-IN500A-EN-P - September 2002
Additional Redundant Server Procedures 6-21
Depending on your configuration, this may take some time to complete.
7. Wait for the synchronization to complete (“Synchronization Complete”
prompt appears) and verify that the display shows simulated Green
LED indications for the following states:
Primary Server
• Running
Backup Server
• Synchronized
• Running
Link Status
• Link 0 (LNK00) - OK Active link
• Link 1 (LNK01) - OK (Only applies if you are using a dual LAN)
8. Click Station
⇒
Exit.
9. Click Yes to exit Station.
Confirming Databases are Synchronized
1. On SERVERA, click
Start
⇒
Run.
2. Enter this command:
>cmd<
and click OK to open the DOS window.
3. At the DOS prompt, key in this command:
>dual_status<
and press <Enter>.