Hapter, Completing the installation – Rockwell Automation SP600 AC Drive User Manual Version 1.0 User Manual
Page 97
 
Completing the Installation
8-1
C
HAPTER
8
Completing the Installation
This chapter provides instructions on how to perform a final check of 
the installation before power is applied to the drive.
8.1
Checking the Installation
To verify the condition of the installation:
Step 1.
Turn off, lock out, and tag the input power to the drive. 
Wait five minutes.
Step 2.
Verify that the DC bus voltage is zero. See section 13.1.
Step 3.
If a function loss coast-stop pushbutton has been 
installed, verify that it has been wired correctly. 
Step 4.
Remove any debris, such as metal shavings, from around 
the drive.
Step 5.
Check that there is adequate clearance around the drive.
Step 6.
Verify that there is nothing mounted behind the drive.
!
ATTENTION: Only qualified electrical personnel familiar with 
the construction and operation of this equipment and the 
hazards involved should start and adjust it. Read and 
understand this manual in its entirety before proceeding. 
Failure to observe this precaution could result in severe bodily 
injury or loss of life.
!
ATTENTION: DC bus capacitors retain hazardous voltages 
after input power has been disconnected. After disconnecting 
input power, wait five minutes for the DC bus capacitors to 
discharge and then check the voltage with a voltmeter to 
ensure the DC bus capacitors are discharged before touching 
any internal components. Failure to observe this precaution 
could result in severe bodily injury or loss of life.
ATTENTION: You must provide an external, hardwired 
emergency stop circuit outside of the drive circuitry. This circuit 
must disable the system in case of improper operation. 
Uncontrolled machine operation can result if this procedure is 
not followed. Failure to observe this precaution could result in 
bodily injury.