Step 7.

Verify that the wiring to the terminal strip and the power
terminals is correct.

Step 8.

Check that the wire size is within terminal specification
and that the terminals are tightened properly.

Step 9.

Check that user-supplied branch circuit protection is
installed and correctly rated.

Step 10. Check that the incoming power is rated correctly.

Step 11. Check the motor installation and length of motor leads.

Step 12. Disconnect any power correction capacitors connected

between the drive and the motor.

Step 13. Check that the rating of the transformer (if used) matches

the drive requirements and is connected properly.

Step 14. Verify that a properly sized ground wire is installed and a

suitable earth ground is used. Check for and eliminate
any grounds between the motor frame and the motor
power leads. Verify that all ground leads are unbroken.

Step 15. Uncouple the motor from any driven machinery.

8.2

Powering Up after Installation is
Complete

To verify that the drive is installed correctly and is receiving the
proper line voltage:

Step 1.

Turn the drive’s input power disconnect to the On position.

Step 2.

Apply power to the drive.

Step 3.

Follow the start-up procedure in chapter 10.