ProcessLogix Client Installation and Upgrade
Procedures

Introduction

Two levels of the ProcessLogix Client workstation software installation
are available:

• Operator Workstation
• Engineering Workstation

Operator Workstation allows remote connections to the ProcessLogix
Server.

Engineering Workstation has all the functionality of the Operator
Workstation but also includes the ProcessLogix Engineering Tools.
From the Engineering Workstation, an engineer using Control Builder
can remotely access and modify the 1757-PLX52 ERDB. All installation
scenarios apply to both Operator Workstations and Engineering
Workstations.

IMPORTANT

Original releases of the NT 4.0 Operating system
could not have boot partitions larger than 4 GB.
Later, fixes were applied for NT 4.0 to have a 7.8 GB
boot partition.

Windows 2000 operating systems can have a 32 GB
boot partition natively, and larger partitions with
certain hardware configurations.

ProcessLogix R510.0 Client Software requires that the
boot partition be at least 4 GB. If your existing
system’s boot partition is less than 4 GB, you must
complete a clean machine installation to extend the
boot partition size after completing the data
preservation steps included in this section.

Systems with 4GB or greater boot partitions can
proceed with the installation procedure. However,
you may want to consider a clean install to extend
the boot partition size.