Commissioning

5-1

48XX/49XXSHB0399

5

Commissioning

5.1

Initial switch-on

Stop!

Prior to initial switch-on of the controller, check the wiring for completeness,
short-circuit, and earth fault:

( Power connection:

- Supply via terminals L1, L2 and L3

- Separate field supply (if available)

( Field connection
( Armature connection
( Feedback system (resolver, incremental encoder, ¡)
( Control terminals:

- Controller enable: Terminal X2/28 (reference potential: X2/39)

- Selection of direction of rotation Terminal X2/21 or X2/22

(reference potential: X2/39)

- Setpoint selection

- with internal voltage supply: bridge between X2/39 and X3/40

( Maintain the switch-on sequence!

Note!

( All controllers described are factory set. A DC shunt motor with attached

tacho can be driven as a speed-controlled drive with tacho feedback
without further settings after entering the rated field current (see nameplate).
The motor must comply with the following:

- V

mains

= 420V

- n

rated

= 3000 rpm

- V

tacho

= 20V / 1000 rpm

( Simple adaptation to other machine data or special requirements: Use the

following for commissioning:

- Operating unit of the controller or

- LEMOC2 (PC program by LENZE)

Show/Hide Bookmarks