Adding other components

Copying and inserting nodes of the same series

9.1.1

Establishing the connection between the visualisation and the FB

How to connect the visualisation to the FB:

1. Select the required FB with a double-click ( ).

2. Click the Wildcard button in the Visualisations dialog box

(

).

3. Replace wildcard

4. Confirm with OK ( ).

After integrating Drive_1(PRG) in the PLC_PRG(PRG) program, error-free compiling and

downloading it to the PLC, the extended controller can be controlled manually.

In the visualisation resources part

(Visualisations tab), you can...
– ...then copy the B_Manual part
– ...and rename it for instance to

B_Manual_1.

After this, establish the wildcard (the

connection to the function block).