Commissioning

Before you start

6

l

102

EDBCSXA064 EN 3.2

6

Commissioning

6.1

Before you start

)

Note!

ƒ

The use of a Lenze motor is assumed in this description of the
commissioning steps. For details on the operation with other motors see

^ 132.

ƒ

The description is based on operation with the Lenze programs "Drive PLC
Developer Studio" (DDS) and "Global Drive Control" (GDC). The parameters
are displayed in online mode, i.e. GDC can directly access the codes of the
axis module.

Prior to initial switch−on of the drive system, check the wiring for completeness,
short−circuit, and earth fault:

ƒ

Power connection:
– Polarity of the DC−bus voltage supply via terminals +UG, −UG

ƒ

Motor connection:
– In−phase connection to the motor (direction of rotation)

ƒ

Wiring of safe torque off" (formerly "safe standstill")

ƒ

Feedback system

ƒ

Control terminals:
– Wiring adjusted to the signal assignment of the control terminals.