Melsec-q, 12 control sub functions, 4] precautions during control – MITSUBISHI ELECTRIC Mitsubishi Programmable Logic Controller QD75D User Manual

Page 486: 5] setting the op shift function, Remark

Advertising
background image

12 - 10

MELSEC-Q

12 CONTROL SUB FUNCTIONS

(2) OP shift operation at the "

Pr.47

Creep speed"

(When "

Pr.56

Speed designation during OP shift" is 1)

When the " Pr. 53 OP
shift amount" is negative

When the " Pr. 53 OP
shift amount" is positive

Pr. 44 OPR
direction

Zero point

Machine OPR start

Near-point dog

Zero signal

OP

Pr. 47 Creep
speed

Fig. 12.7 OP shift operation at the creep speed

[4] Precautions during control

The following data are set after the OP shift amount is complete.

OPR complete flag ("

Md.31

Status: b4)

Md.20

Current feed value

Md.21

Machine feed value

Md.26

Axis operation status

Md.34

Movement amount after near-point dog ON ("

Pr.53

OP shift

amount" is not added.)

OPR request flag (

Md.31

Status: b3) is reset after completion of the OP

shift.

[5] Setting the OP shift function

To use the "OP shift function", set the required details in the parameters shown in
the following table, and write them to the QD75.
When the parameters are set, the OP shift function will be added to the machine
OPR control. The set details are validated at the rising edge (OFF ON) of the
PLC READY signal (Y0).

Setting item

Setting

value

Setting details

Factory-set
initial value

Pr.53

OP shift amount

Set the shift amount during the OP shift.

0

Pr.56

Speed
designation
during OP shift

Select the speed during the OP shift

0:

Pr.46

OPR speed

1:

Pr.47

Creep speed

0

Refer to Section 5.2 "List of parameters" for setting details.

REMARK

Parameters are set for each axis.

It is recommended that the parameters be set whenever possible with GX
Configurator-QP. Execution by sequence program uses many sequence programs
and devices. The execution becomes complicated, and the scan times will
increase.

Advertising