background image

12 - 89

MELSEC-Q

12 CONTROL SUB FUNCTIONS

V

t

Ts

Tw

t

Ts

Ts

1

Feed shaft

Cutter shaft

Feed shaft
start request

Cutter shaft
start request

Start

time

Start

time

Start

time

Stop time

2

Fig. 12.50 Operation timings of system example

The cutter shaft starts from the moment the feed shaft has completed feeding the

stock "

1

", and the feed shaft starts from the moment the cutter shaft has

returned to the standby position "

2

". Actually, however, there is a delay of start

time Ts (6 to 7ms) from when the QD75 receives a start request until it outputs

pulses. The system's tact time can be reduced by the shortening of this delay

with the Pre-reading start function.

In Fig. 12.50, the feed shaft stands by during the stop time Tw.

Hence, pre-reading of the next data starts during the stop time Tw. If Tw is a

certain period of time, the analysis of the next data is completed during that

period, and the system is placed in an execution prohibition flag OFF waiting

status. Therefore, replacing the positioning start timing at

2

with the execution

prohibition flag OFF allows the time from when the axis operation request turns

ON until pulse output starts to be reduced to within 3ms in the sequence

program. (Refer to Fig. 12.48)