4.2 Preparation (step 1)

4.2.3 Test Operation

4-6

4.2.3 Test Operation

Confirm that the machine controller can command axis servo ON/OFF and jog operation.

( 1 ) Starting and Connecting MPE720 Ver.6

Launch MPE720 Ver.6 and click “1:Ethernet(LP)192.168.1.1” to connect to the controller.
For more information on the communications settings, refer to Appendix F Simple Connection Function of the Engi-
neering Tool
.

When the connection is complete, the display will change from offline to online.

( 2 ) Operating Manually in the Test Operation Screen

1.

Click System in the subwindow and double-click Axis Configuration - Test Run to display a warning
dialog a box for the test run. Click the Accept Button.