2 profibus-dp, 1 before switching on, Profibus−dp – Lenze EPM−T9XX Modular system User Manual

Page 291: Before switching on, Commissioning

Advertising
background image

PROFIBUS−DP

Before switching on

11

Commissioning

11.2

11.2.1

L

11.2−1

EDSPM−TXXX−9.0−11/2009

11.2

PROFIBUS−DP

11.2.1

Before switching on

Prior to supply voltage connection, check

l

the wiring for completeness, short circuits and earth faults

l

the wiring of the fieldbus

– A bus terminating resistor has to be connected to the first and the last

node.

l

spatial cable separation from signalling and mains cables.

)

Note!

After connecting the supply voltage, the modules of the I/O
system IP20 are initialised. During the initialisation, the modules
cannot be parameterised.

l

Initialisation time: approx. 10 s