Hardware

(1) Cylinders (carrier gas, standard gases, etc.)

These cylinders are fi lled with a carrier gas or standard gas.
The maximum fi lling pressure is limited to 15 MPa considering the strength of the cylinders.

(2) Regulator for cylinder

This valve reduces a cylinder pressure to a safe degree to facilitate handling. The valve is directly
mounted to the cylinder.

(3) Stop valve

This valve shuts down the lines for the sample gas, instrument gas, and so on. It is operated
manually.

(4) Dehumidifi er

Any moisture in the carrier gas affects the columns. Therefore, if the carrier gas contains
moisture over 10 ppm, it is recommended to use a desiccant, such as a molecular sieve, to
prevent deterioration of the columns.

(5) Vent stacks

These are pipes to discharge sample bypass vent, sample vent, backfl ush vent, forefl ush vent,
detector vent, measurement gas vent, and others to the atmosphere collectively.
Direct the exhaust gas to an area where the gas suffi ciently disperses and diffuses before
discharging.

(6) Regulator for sample

This valve reduces the sample pressure to a specifi ed degree.
To vaporize a liquid sample, use a regulator with a steam-heated vaporizer.

(7) Pipings

The pipes for the sample inlet, carrier gas inlet, standard gas inlet, air for valve driving, air for
FID/FPD, FID/FPD hydrogen, steam, sampling bypass, and various vents are provided.

(8) Joints

The joints are used to connect pipes.

1.4

Gases Required for Operation

The following gases are required for the analyzer:

(1) Sample gas

The gas to be analyzed from the process line

(2) Carrier gas

Prepare a gas cylinder for the carrier gas. Keep spare cylinders at hand, too.