● In the case where a stream sequence change command is received during the run mode in

the stream sequence status [1A2]

The measurement status is changed to the requested stream sequence status when the

measurement of the currently-measured stream is completed.

In this case, the operation mode remains unchanged from the run mode.

* Requests for changes to the same stream sequence number are invalid.

● In the case where a stream sequence change command is received during the pause mode

in the stream sequence status [1A6]

The measurement status is immediately changed to the requested stream sequence status.
In this case, the operation mode changes to the stop mode and valves are all closed (turned

off).

* Requests for changes to the same stream sequence number are invalid.

Stop

Run

W4

W5

W1

W2

W3

S2

S1

S5

S4

[1A1]

[1A2]

Time

Stream sequence 1

Stream sequence 2

Stream sequence 1

Assinning stream

sequence 2

Assinning stream sequence 1

Run command

Stop

Pause

Run

W4

W5

W1

W2

W3

S2

S1

S5

S4

[1A6]

[1A2]

Time

Stream sequence 1

Stream sequence 2

Stream sequence 1

Assinning stream

sequence 2

Assinning stream sequence 1

Run command

● In the case where a stream specifi cation change command (for continuous measurement)

is received during the run mode in the stream sequence status [1B2]

The measurement status is changed to the requested stream specifi cation status (for

continuous measurement) when the measurement of the currently-measured stream is
completed.

In this case, the operation mode remains unchanged from the run mode.

Run

W4

W1

W2

S2

S1

S4

W4

S4

W4

S4

W4

S4

W4

[1B2]

Time

Stream sequence 1

Stream specification 4 (Continuous)

Assinning stream specification 4 (Continous)

● In the case where a stream specifi cation change command (for N times of measurement) is

received during the run mode in the stream sequence status [1C2]

The measurement status is changed to the requested stream specifi cation status (for

N times of measurement) when the measurement of the currently-measured stream is
completed.

In this case, the operation mode changes from the run mode to the stop mode when the Nth

round of the specifi ed measurement is completed.