Part 2 Startup Chapter

Chapter 1 Overview

241

Part 2 Startup Chapter

1.2 Startup Procedure

The basic startup procedure for a ROBONET system is shown below.

(1) Installation (Refer to 2.1)

Mount on a DIN rail the Gateway R unit, controller unit and/or simple absolute R unit as required, interconnect

the units, and install the units in a control panel.

p

(2) Wiring (Refer to 2.2)

Wire the ROBONET 24-V power supply, field network, actuator drive line and encoder line.

p

(3) Set the address of the controller unit (Refer to Chapter 3)

p

(4) Perform an absolute reset (when the simple absolute R unit is used) (Refer to 4.2 to 4.5)

Perform an absolute reset to establish an absolute system.

p

(5) Set up the ROBONET (Refer to 5.2)

Use the ROBONET gateway parameter setting tool to set the station number, baud rate, operation mode of

each axis, etc.

p

(6) Set up the master in the field network (Refer to 5.3)

Set various items using a dedicated tool appropriate for each field network.

p

(7) Create a controller position table (Refer to 5.4)

(Positioner mode or simple direct mode)

p

(8) Create a PLC ladder sequence

p

(9) Trial operation

p

(10) Full-scale operation

-265-