Lenze E94ARNE Regenerative power supply User Manual

Page 16

Advertising
background image

9400 regenerative power supply module | Parameter setting

Commissioning

Short setup

16

L

EDS94ARNExxxx EN 2.3 - 06/2014

How to carry out the commissioning with the »Engineer«:

1. Start the »Engineer«.
2. Select the procedure in the Start-up wizard.

• For instance, select the option "Select component from catalog".

3. Add the corresponding components from the catalog to the project:

Regenerative power supply module

Available device modules

Regenerative power supply module application

Project view example in the »Engineer«:

4. Select the regenerative power supply module in the Project view.
5. Change to the Application parameters tab in the Workspace.

6. If the mains voltage is not 400/415 V, adapt the Lenze setting accordingly in the

Mains voltage list field.
Note: A change of the setting in

C00173

also has an impact on the permissible

device utilisation! In the chapter "Rated data" of the Hardware Manual, the device

types and their permissible device utilisation at different mains voltages and

switching frequencies are specified.

Advertising