Final works

Initial commissioning on 400 V mains voltage

7

308

EDS94SPP101-7.1

7.7

Final works

7.7.1

Initial commissioning on 400 V mains voltage

After the installation has been carried out according to the Mounting Instructions, the

regenerative power supply module can be operated on a mains voltage of 400 V.
The regenerative feedback is activated via the digital input RFR.
How to proceed:
1. Switch on 24 V supply voltages.

– for the mains filter
– for the regenerative power supply module (optional)

2. Switch on 400 V mains voltage.
3. Activate/deactivate regenerative feedback via the digital input RFR.

7.7.2

Initial commissioning on 230 V or 500 V mains voltage

For operation on a mains voltage of 230 V or 500 V, first the mains voltage within the

regenerative power supply module has to be set. The setting is effected in C00173 and can

be carried out using a keypad or the Lenze PC software »Engineer«.
For commissioning you require:

ƒ

An EZAEBKx00xkeypad,

or

ƒ

A computer with Windows® operating system (XP or 2000)

ƒ

The Lenze PC software »Engineer«

ƒ

A connection to the regenerative power supply module via an interface, e. g.
– Diagnostic interface X6 with USB diagnostic adapter
– CAN system bus
– Communication modules in the expansion slots M1/M2

ƒ

The software manual for the technology application used

ƒ

The communication manual (KHB) for the network of the automation platform

ƒ

Switch on 24 V supply voltages:
– for the mains filter
– for the regenerative power supply module

After the setting has been carried out according to the mains voltage available:
1. Switch on mains voltage.
2. Activate/deactivate regenerative feedback via the digital input RFR.

7.7.3

Further settings

Follow the instructions of the software and/or read the documentation for the

parameterisation of the regenerative power supply module.