Figure 6.14.6.3: example- operating point of drive – GE Industrial Solutions DV-300 DC Drive Users Manual User Manual

Page 248

Advertising
background image

GEI-100332Ga

——— FUNCTION DESCRIPTION ———

6

120

Diagram

= 0.75

for05

Base current

I

dAN

82 A

110 A

=

This means that the diagram for the converters 110 A ... 185 A with a Base current = 75

% has to be considered for the calculation.

Operating point

Basis: rated data of the converter

Overload current = 82A

. 1.8 = 147.6A

for06

= 1.34

for07

Overload current

I

(of converter)

d A N

147.6 A

110A

=

Overload factor

=

= 0.16

for08

Overload time

Pause time + Overload time

1s

5s + 1s

=

1 s

Base current = 75 % I

2,00

1,75

1,50

1,25

1,00

Overload

curren

t/

I

dAN

dAN

0,1

0,2

0,3

0,4

0,5

0,6

0,7

0,8

0,9

1,0

Overload time / (Pause time + Overload time)

Overload time

Figure 6.14.6.3: Example- Operating point of drive

The calculated operating point is below the corresponding curve for an overload time of 1 s. Therefore the con-

verter is suitable for the application. The following two settings are possible:

Full load curr

82 A

or

110 A

Enable overload

Enabled

Overload current

180 %

or

134 %

Base current

100 %

or

75 %

Overload time

1 s

Pause time

5 s

n

ote

!

The percentages for Overload current and Base current are referred to Full load curr and

not to the converter rated current!