5. Commissioning
5-26
Festo P.BE-MTR-DCI-PB-EN en 1209a
5.4
Overview of commissioning on the PROFIBUS
The following steps are required for commissioning the MTR-
DCI as a fieldbus station:
1. Set the PROFIBUS address on the MTR-DCI:
•
On the control panel (only with MTR-DCI-...-H2, see
Section 5.2.7), or
•
With the Festo Configuration Tool (see FCT help).
Permitted address range: 0 ... 125 (in some cases
limited by the DP master used).
Modification by a DP master is not possible.
2. Install the GSD file and icon files, see section 5.5.1.
3. Configure the PROFIBUS master with the relevant con-
figuration software (e.g. with STEP 7 Hardware Configura-
tor), see section 5.5.3.
4. Test the fieldbus connection in online mode.
Details can be found in the following sections: