5. Commissioning

5-5

Festo P.BE-MTR-DCI-PB-EN en 1209a

Before commissioning the drive make sure that:

The work space is of sufficient size for operation with
a work load

The work load does not collide with the motor or the
gear of the axis when the slide moves into the end
position

Please observe the notes in the operating instructions for
your axis.

Switching on

Note
Note that the tolerance for the supply voltage must be
observed. The tolerance must also be observed directly at
the operating voltage connection of the MTR-DCI
(see appendix A.1).

Note

When the power supply is switched off, wait for approx.
5 seconds before switching the device on again.

1. Switch on the power supply for the MTR-DCI. When the

power supply is switched on, the MTR-DCI automatically
carries out an internal check.

2. Carry out parameterising and commissioning with the

control panel or the FCT, as described in the following
chapters or in the FCT/plugin help.

3. In order to complete commissioning note the instructions

for operation in the FCT/plugin help and in section 5.9.