Overview of initial commissioning – Festo Контроллеры двигателя SFC-LAC User Manual
Page 110
![background image](/manuals/464473/110/background.png)
5. Commissioning
5−8
Festo GDCP−SFC−LACI−CO−EN en 0812NH
5.2
Commissioning with the control panel (only type SFC−LACI−...−H2)
Information on the button functions and the menu structure
of the control panel can be found in Chapter 4.
Overview of initial commissioning
Commissioning steps
Chapter
1 Before switching on: make sure that there is no active
ENABLE signal on the controller interface.
2 Switch on the SFC−LACI, configure the fieldbus interĆ
face, then Reset.
3 Set the parameters for homing:
Ĉ Homing method
Ĉ Search speed to homing point
Ĉ Positioning speed to axis zero point
4 Activate control panel device control [HMI = on]
5 Carry out homing.
5.2.4
6 Teach the axis zero point.
7 Teach software end positions.
8 Set the tool mass.
9 Enter positioning records.
10 Carry out a test run. Check motion behaviour,
reference points and working range. Optimise as
required.
5.2.9
11 Check the function of the controller interface and note
the instructions on operation.
Tab. 5/1: Commissioning steps