87

3

Commissioning

3.9

Commissioning of the "Switch-off positioning" technology application

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

3.9.5

Saving parameter settings safe against mains failure

The parameter set must be saved to the device safe against mains failure to prevent parameter

settings becoming lost due to mains switching.

Save parameter set.

3.9.6

Enable controller and test application

If the controller is in the "

SwitchedOn

" status:

1. Enable controller: Set terminal X5/RFR to HIGH level or close contact.

• If there is no other active source for the controller inhibit, the controller changes from the

"

SwitchedOn

" status to the "

OperationEnabled

" status.

• The Diagnostics tab and

C00158

display all active sources for the controller inhibit.

2. Select the respective control signals via the digital inputs.

Related topics:

"Inhibit at power-on" auto-start option

( 122)

Trouble-shooting during commissioning

( 54)

Diagnostics & error management

( 615)

Stop!

Before stipulating a speed setpoint, check whether the brake in the form of a holding

brake on the motor shaft has been released!

Note!

If the controller is enabled and the "Inhibit at power-on" auto-start option is activated in

C00142

(Lenze setting) when the mains is connected, the controller remains in the

"

ReadyToSwitchOn

" state.

To be able to change to the "

SwitchedOn

" status, the controller enable must be

deactivated first: set terminal X5/RFR to LOW level.

Note!

Observe the actual speed value (display in

C00051

) as well as the

LED status displays

.

( 616)