1 Prerequisites and Visual Inspection

1.1 Prerequisites

1

Prerequisites and Visual Inspection

1.1

Prerequisites

The following prerequisites must be fulfilled prior to initial start-up:

•

Electrical and mechanical installation of the machine must have been completed and the
axes prepared for operation.

The following points must be confirmed by the customer!

•

Customer PLC program operational and pretested.

•

Measuring system installed and wired as far as SINUMERIK.

•

Cables connected to the machine. Cable shields run to the control neutral point as per
Interface Description. Flexible earth wires installed. Earthing concept observed (inspect
carefully!).

•

Customer personnel support for work on the interface unit, work on the machine, machine
operation and customer produced PLC program.

Recommendation:

Prelimit travel ranges (greater clearance distances) by displacing the end stop
(EMERGENCY STOP cam).

•

The specified machine data is available.

•

Data carriers are available for checking machine specific functions.

1.2

Visual inspection

General remarks:

Refer to the "EMC Guidelines", Order No. 6FC 3987-7DB

These guidelines provide the following information:

•

Why are EMC guidelines necessary?

•

What external interference sources affect the control?

•

How can interference be prevented?

•

Practical examples for an interference free installation.

•

How should electronically endangered components (EEC) be handled?

•

How can an EMC problem be rectified?

•

What standards are relevant to EMC?