Commissioning

3.7

Commissioning of the "Actuating drive speed" technology application

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

3.7

Commissioning of the "Actuating drive speed" technology application

[3-1]

Block diagram for wiring the commissioning example for the "Actuating drive speed" application

Commissioning steps
Find a description of the commissioning steps of the "Actuating drive speed" technology application

below.
Please observe the sequence of the steps in the following chapters and follow them through

carefully. This will help you to commission your controller quickly and as safely as possible:

Prepare controller for commissioning

( 60)

Creating an »Engineer« project & going online

( 61)

Parameterising the motor control

( 62)

Parameterise application

( 63)

Note!

Take all the necessary safety precautions before you carry out the following

commissioning steps and switch the device on!

Safety instructions with regard to commissioning

( 53)

System constellation

X3/AR

Reference voltage (10 V) for analog signals

X3/A1U

Speed setpoint selection (slider of setpoint potentiometer R)

• Scaling: 10 V ≡ 100 % ≡ 1500 rpm

1

(for a 4-pole motor)

X3/GA

Ground potential (GND) for analog signals

X5/RFR

Controller enable

X6

Diagnostic interface for connecting the USB diagnostic adapter

8400 TopLine

X61

X6

DIAG

AR A1U GA

X3

24I RFR DI1 DI2

X5

DI3 DI4 DI5 DI6 DI7

U V W

X6

M

3~

i

R

1k

... 10k

W

W