Commissioning

3.8

Commissioning of the "Table positioning" technology application

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

3. Connect USB diagnostic adapter.

4. Switch on voltage supply of the controller.

• Without motor operation: Connect external 24 V supply.
• With motor operation: Connect mains voltage.

If the green "DRV-RDY" LED is blinking and the red "DRV-ERR" LED is off, the controller is ready for

operation and commissioning can proceed.

Related topics:

Commissioning notes for external 24 V supply

( 50)

Automatic restart after mains connection/trouble...

( 119)

LED status displays

( 554)

Danger!

For the commissioning with motor operation observe that no setpoint is applied before

connecting the mains voltage.
In the Lenze setting the "Inhibit at power-on" auto-start option has been deactivated in

C00142

, i.e. the motor can directly start up if the controller is enabled after mains

connection!