9 pto work coordinate – Rockwell Automation 8520-ARM2 9/Series CNC AMP Reference Manual Documentation Set User Manual
Page 442
Power-up G-code Parameters
Chapter 19
19-10
Function
This parameter selects the default work coordinate system. It determines
the work coordinate system that is activated at power-up, control reset, or
when a G92.1 is programmed. The default work coordinate system may
also be be activated when the control executes an end-of-program block
(M02/M30) if the the value of parameter Reset Coord Offsets on
M02/M30 is “yes.”
Axis
Parameter Number
Single Process
Process 1
Process 2
All
[15]
[20015]
[21015]
Range
Selection
Result
Selection
Result
(a)
None
(f)
G58
(b)
G54
(g)
G59.1
(c)
G55
(h)
G59.2
(d)
G56
(i)
G59.3
(e)
G57
Notes
This is a global parameter. The value set here applies to all axes.
For dual--processing controls, this is a per process parameter. The value set
in the parameters applies to all of the axes assigned to that process.
19.9
PTO Work Coordinate