2 notes on project planning, 1 supply forms / electrical supply conditions, Notes on project planning – Lenze E82xVxxxKxxxxx User Manual

Page 99: Supply forms / electrical supply conditions, Electrical installation

Advertising
background image

Electrical installation

Notes on project planning

Supply forms / electrical supply conditions

6

l

99

EDS82EV903 EN 3.0

6.2

Notes on project planning

6.2.1

Supply forms / electrical supply conditions

Please comply with the operating conditions of each mains type:

Mains

Type

Restrictions

Notes

With earthed neutral
(TT/TN systems)

E82xVxxxKxxxxx

l

None

With insulated star
point (IT systems)

E82xVxxxKxB1xx

1)

(15 ... 90 kW)

l

Operation with mains filters or RFI
filters is not permissible

2)

l

Installation of a CE−typical drive
system: For the installation of
drives to IT systems, the same
conditions apply as for the
installation to TT/TN systems

l

According to EN 61800−3, limit
values regarding RFI emission for
high frequencies are not specified
for IT systems.

l

During DC−bus operation, central
supply with 9340 regenerative
power supply modules is not
possible.

All other

l

Operation not permissible

With earthed phase

E82xVxxxKxxxxx

l

As in IT systems

l

Not UL−approved

DC supply via +U

G

/−U

G

E82xVxxxKxxxxx

l

The DC voltage must be
symmetrical to PE

l

The controller will be destroyed if
the +U

G

conductor or −U

G

conductor is earthed.

1)

The "IT systems" version which is available in a power range from 15 to 90 kW also has an insulated structure, just
like the IT system. That way, insulation monitoring is prevented from responding, even if multiple frequency
inverters are installed. The frequency inverters have an increased electric strength so that damage to the inverter is
also prevented in the event of an insulation fault or earth fault in the supply system. Operational reliability of the
system remains ensured.

2)

Operation with Lenze mains filters or RFI filters is not allowed because they contain components connected to PE.
The safety concept of the IT system would thus be set off.